Perth City Deal - Roe Street Enhancement 2021-2022

Share on Facebook Share on Twitter Share on Linkedin Email this link

As part of the Perth City Deal CBD Transport Plan, the highly anticipated upgrade to Roe Street commenced construction at the end of May 2021, with a scheduled completion in Spring 2022.

The upgrade, which is being completed by appointed contactor Civcon and in collaboration with DevelopmentWA, will facilitate the upgrade of critical infrastructure and revitalised streetscapes.

The completed project will complement the Perth City Link development, reconnect the Central Business District with Northbridge and facilitate regeneration of the area. While the entire project will be constructed by Civcon, DevelopmentWA and the City of Perth will be responsible for delivering two separate projects (referred to as 'Package A' and 'Package B').

The projects have been delivered simultaneously to minimise disruption, with a coordinated approach being taken to complete the infrastructure upgrades (Package A) prior to the street beautification project (Package B) and will be completed in sections over various stages.

Please note that there will be pedestrian and cycle path detours in place.

Rolling Construction Updates

Upcoming full 24 hour road closures for east and west bound traffic along Roe Street (between William and King Streets) - Monday 11 July to Sunday 24 July 2022. Please see detour map 1 below.

What is happening and when?

There are several consecutive projects commencing through between 20 June and 16 September 2022. Civcon has scheduled the following activities:

It is important to note that all works noted below are subject to change (particularly due to weather impacts).

Proposed Start & Finish dates of worksLocationPlanned WorksRoad closures
Monday 27 to Wednesday 29 June 2022
Beaufort StreetSignal CommissioningFull intersection closure - bus route only
Please watch VMS boards and follow the instruction of onsite traffic controllers at all times.
CURRENT:
Monday 4 July to Friday 8 July 2022
Beaufort to William Streets

Resurfacing (Westbound)

Westbound road closure
Friday 27 May to Wednesday 1 July 2022

Installation of Granite Kerbing

Paving

Asphalt resurfacing

Removal of the westbound movement on Roe Street between William and Beaufort Street (eastbound only).

Please refer to detour map 2 and follow the direction of onsite traffic controllers.

Reduced footpath width throughout construction and installation of temporary construction fencing.

Access to the CPP Car Park will be available at all times.

Monday 8 August to Friday 12 August 2022
Resurfacing (Eastbound)Eastbound road closure
Monday 13 June to Friday 15 July 2022
William StreetRemoval of temporary kerb
Installation of granite and paving
Westbound closure including William Street Bridge
Monday 20 June to Friday 24 June 2022
MFP and signals installationFull road closure - Roe Street (King to William Streets) (east and west bound)
Monday 1 August to Friday 5 August 2022
Full intersection resurfacingFull Closure
Monday 11 July to Sunday 24 July 2022
Between William and King StreetsSewer Crossing (Western Power)Full and continuous closure for duration of works
Detour map to be provided closer to works commencing


CURRENT:

Monday 4 July to Friday 8 July 2022 &
Monday 11 to Sunday 24 July 2022

Service Installation

Verge reconstruction

Pavement reconstruction and asphalt re-surfacing

Full 24 hours road closures for East and West bound traffic.

Please refer to detour map 1 and follow the direction of the onsite traffic controllers.

Construction noise, footpath detours and installation of temporary construction fencing.

Local driveway access and use of pedestrian crossings will be permitted at all times.
Monday 15 August to Friday 19 August 2022
King & Lake Street IntersectionResurfacing full width (intermediate layer)Full Closure
Friday 16 September 2022
Switch traffic closures to Northern SideNorth Side Closure
Monday 19 to Thursday 22 September 2022
Melbourne to King StreetsResurfacing full width (intermediate layer)Full Closure
Monday 29 August to Friday 16 September 2022


Sewer Crossing

Full Closure

Monday 22 August to 24 August 2022
Fitzgerald to Melbourne StreetsResurfacing full width (intermediate)
Northside closure
Monday 29 August 2022

Switch traffic closures to Northern Side

Full Closure


Night Work

There will be a requirement to perform certain activities outside of normal working hours in order to:

  • Reduce the impact on pedestrians
  • Reduce the impact on businesses and
  • Provide a safe working environment for our personnel.

Temporary road/lane closures and detour maps

Access to businesses, cyclists and pedestrian crossing will be maintained at all times during normal working hours (7am to 5pm) or as required.

Traffic Detours will be in place for the duration of the works schedule and traffic controllers will be on site to guide you. Detour map 1 below:


Detour map 2 below:

Who to contact?

We are committed to working with stakeholders to minimise the impacts of this essential work and everything possible will be done to minimise disruption. While we will endeavor to complete the work as quickly as possible if you have any concerns, please refer to:

Civcon Senior Project Engineer – Marinko Knezovic – 0478 761 817


Project Details

Package A (DevelopmentWA project) will consist of:

  • Concrete and asphalt removal and reconstruction
  • Existing service location and investigation
  • Underground services installation (including trenching, pit and pipe installation)

Package B (City of Perth) project will consist of:

  • Creation of wider footpaths to accommodate increased pedestrian movement and activity, including alfresco dining;
  • New street lighting and CCTV assets to improve public safety and support the night-time economy;
  • Protected uni-directional cycle lanes to improve the safety of cyclists and pedestrians, as well as ensuring integration into the overall cycle network to the city;
  • A narrower street corridor to encourage lower vehicle speeds and to make it easier for pedestrians to cross;
  • 200+ new street trees will be planted to provide shade, urban cooling and greenery; and
  • Brand new paving, street furniture and City of Perth free public Wi-Fi to encourage footfall.


How can I find out more?

  1. Please start by reading our FAQ's to see if your question has been answered
  2. If it hasn't and it is a general question relating to the project, please ask a question below and we will get back to you soon with a response
  3. If it is a specific question about the impact that the project may have on your property or home, please email our Stakeholder Engagement team with your name, address, phone number and business name (if applicable) to ensure we can provide you with a personal response.

What if I urgently need to contact the contractor?

You can contact Civcon directly via the details below:

Justin de Mello - Civcon Project Manager
0401 941 438
justin.demello@civconwa.com.au

As part of the Perth City Deal CBD Transport Plan, the highly anticipated upgrade to Roe Street commenced construction at the end of May 2021, with a scheduled completion in Spring 2022.

The upgrade, which is being completed by appointed contactor Civcon and in collaboration with DevelopmentWA, will facilitate the upgrade of critical infrastructure and revitalised streetscapes.

The completed project will complement the Perth City Link development, reconnect the Central Business District with Northbridge and facilitate regeneration of the area. While the entire project will be constructed by Civcon, DevelopmentWA and the City of Perth will be responsible for delivering two separate projects (referred to as 'Package A' and 'Package B').

The projects have been delivered simultaneously to minimise disruption, with a coordinated approach being taken to complete the infrastructure upgrades (Package A) prior to the street beautification project (Package B) and will be completed in sections over various stages.

Please note that there will be pedestrian and cycle path detours in place.

Rolling Construction Updates

Upcoming full 24 hour road closures for east and west bound traffic along Roe Street (between William and King Streets) - Monday 11 July to Sunday 24 July 2022. Please see detour map 1 below.

What is happening and when?

There are several consecutive projects commencing through between 20 June and 16 September 2022. Civcon has scheduled the following activities:

It is important to note that all works noted below are subject to change (particularly due to weather impacts).

Proposed Start & Finish dates of worksLocationPlanned WorksRoad closures
Monday 27 to Wednesday 29 June 2022
Beaufort StreetSignal CommissioningFull intersection closure - bus route only
Please watch VMS boards and follow the instruction of onsite traffic controllers at all times.
CURRENT:
Monday 4 July to Friday 8 July 2022
Beaufort to William Streets

Resurfacing (Westbound)

Westbound road closure
Friday 27 May to Wednesday 1 July 2022

Installation of Granite Kerbing

Paving

Asphalt resurfacing

Removal of the westbound movement on Roe Street between William and Beaufort Street (eastbound only).

Please refer to detour map 2 and follow the direction of onsite traffic controllers.

Reduced footpath width throughout construction and installation of temporary construction fencing.

Access to the CPP Car Park will be available at all times.

Monday 8 August to Friday 12 August 2022
Resurfacing (Eastbound)Eastbound road closure
Monday 13 June to Friday 15 July 2022
William StreetRemoval of temporary kerb
Installation of granite and paving
Westbound closure including William Street Bridge
Monday 20 June to Friday 24 June 2022
MFP and signals installationFull road closure - Roe Street (King to William Streets) (east and west bound)
Monday 1 August to Friday 5 August 2022
Full intersection resurfacingFull Closure
Monday 11 July to Sunday 24 July 2022
Between William and King StreetsSewer Crossing (Western Power)Full and continuous closure for duration of works
Detour map to be provided closer to works commencing


CURRENT:

Monday 4 July to Friday 8 July 2022 &
Monday 11 to Sunday 24 July 2022

Service Installation

Verge reconstruction

Pavement reconstruction and asphalt re-surfacing

Full 24 hours road closures for East and West bound traffic.

Please refer to detour map 1 and follow the direction of the onsite traffic controllers.

Construction noise, footpath detours and installation of temporary construction fencing.

Local driveway access and use of pedestrian crossings will be permitted at all times.
Monday 15 August to Friday 19 August 2022
King & Lake Street IntersectionResurfacing full width (intermediate layer)Full Closure
Friday 16 September 2022
Switch traffic closures to Northern SideNorth Side Closure
Monday 19 to Thursday 22 September 2022
Melbourne to King StreetsResurfacing full width (intermediate layer)Full Closure
Monday 29 August to Friday 16 September 2022


Sewer Crossing

Full Closure

Monday 22 August to 24 August 2022
Fitzgerald to Melbourne StreetsResurfacing full width (intermediate)
Northside closure
Monday 29 August 2022

Switch traffic closures to Northern Side

Full Closure


Night Work

There will be a requirement to perform certain activities outside of normal working hours in order to:

  • Reduce the impact on pedestrians
  • Reduce the impact on businesses and
  • Provide a safe working environment for our personnel.

Temporary road/lane closures and detour maps

Access to businesses, cyclists and pedestrian crossing will be maintained at all times during normal working hours (7am to 5pm) or as required.

Traffic Detours will be in place for the duration of the works schedule and traffic controllers will be on site to guide you. Detour map 1 below:


Detour map 2 below:

Who to contact?

We are committed to working with stakeholders to minimise the impacts of this essential work and everything possible will be done to minimise disruption. While we will endeavor to complete the work as quickly as possible if you have any concerns, please refer to:

Civcon Senior Project Engineer – Marinko Knezovic – 0478 761 817


Project Details

Package A (DevelopmentWA project) will consist of:

  • Concrete and asphalt removal and reconstruction
  • Existing service location and investigation
  • Underground services installation (including trenching, pit and pipe installation)

Package B (City of Perth) project will consist of:

  • Creation of wider footpaths to accommodate increased pedestrian movement and activity, including alfresco dining;
  • New street lighting and CCTV assets to improve public safety and support the night-time economy;
  • Protected uni-directional cycle lanes to improve the safety of cyclists and pedestrians, as well as ensuring integration into the overall cycle network to the city;
  • A narrower street corridor to encourage lower vehicle speeds and to make it easier for pedestrians to cross;
  • 200+ new street trees will be planted to provide shade, urban cooling and greenery; and
  • Brand new paving, street furniture and City of Perth free public Wi-Fi to encourage footfall.


How can I find out more?

  1. Please start by reading our FAQ's to see if your question has been answered
  2. If it hasn't and it is a general question relating to the project, please ask a question below and we will get back to you soon with a response
  3. If it is a specific question about the impact that the project may have on your property or home, please email our Stakeholder Engagement team with your name, address, phone number and business name (if applicable) to ensure we can provide you with a personal response.

What if I urgently need to contact the contractor?

You can contact Civcon directly via the details below:

Justin de Mello - Civcon Project Manager
0401 941 438
justin.demello@civconwa.com.au

Page last updated: 05 Jul 2022, 09:33 AM