Share Winthrop Avenue Shared Path Project on FacebookShare Winthrop Avenue Shared Path Project on TwitterShare Winthrop Avenue Shared Path Project on LinkedinEmail Winthrop Avenue Shared Path Project link
The City of Perth is pleased to advise construction works for the Winthrop Avenue Shared Path project will commence in early 2023. The delivery of a high-quality shared path along Winthrop Avenue has been a long term goal that was initially identified within the City’s 2018 Transport Strategy. The State Government also identified this as a primary route that represents a key ‘missing link’ in Perth’s long term cycling network. The project is jointly funded by both the Department of Transport and the City of Perth.
The upgrade and construction of this shared path will provide an important cycle link between Aberdare Road and Stirling Highway. Phase 2 of the project (to be commenced in subsequent financial years) will continue this important link up Thomas Street completing the missing connection for cyclists from Mounts Bay Road/ Stirling Highway to the Mitchell Freeway.
This project aims to achieve the following outcomes:
• Continue building upon a connected cycling network within the City of Perth • Provide a safer and compliant shared path linking from Stirling Highway to Aberdare Road • Create more inviting and healthy streets that encourage walking and riding
PROJECT DETAILS
Location: Winthrop Avenue between Stirling Highway and Aberdare Road Date: Mid May 2023– Mid August 2023 Time: 9am – 3pm during the day
Where possible works will be carried out during the day. Night works will occur only when partial lane closures are not permitted. All works at night shall be bound by the Environmental Protection (Noise) Regulations 1997 and the permit requirements issued by the City of Perth.
PROJECT TIMELINE
Work Stages
Dates
Minor tree pruning and removal works (only within the City of Perth road corridor)
Mid May 2023
Demolition and replacement kerbing works
Mid-May to Mid-June 2023
Path construction and service adjustments
Mid- June to Mid August 2023
* All dates are provisional pending permit approvals and suitable weather conditions.
The City of Perth is pleased to advise construction works for the Winthrop Avenue Shared Path project will commence in early 2023. The delivery of a high-quality shared path along Winthrop Avenue has been a long term goal that was initially identified within the City’s 2018 Transport Strategy. The State Government also identified this as a primary route that represents a key ‘missing link’ in Perth’s long term cycling network. The project is jointly funded by both the Department of Transport and the City of Perth.
The upgrade and construction of this shared path will provide an important cycle link between Aberdare Road and Stirling Highway. Phase 2 of the project (to be commenced in subsequent financial years) will continue this important link up Thomas Street completing the missing connection for cyclists from Mounts Bay Road/ Stirling Highway to the Mitchell Freeway.
This project aims to achieve the following outcomes:
• Continue building upon a connected cycling network within the City of Perth • Provide a safer and compliant shared path linking from Stirling Highway to Aberdare Road • Create more inviting and healthy streets that encourage walking and riding
PROJECT DETAILS
Location: Winthrop Avenue between Stirling Highway and Aberdare Road Date: Mid May 2023– Mid August 2023 Time: 9am – 3pm during the day
Where possible works will be carried out during the day. Night works will occur only when partial lane closures are not permitted. All works at night shall be bound by the Environmental Protection (Noise) Regulations 1997 and the permit requirements issued by the City of Perth.
PROJECT TIMELINE
Work Stages
Dates
Minor tree pruning and removal works (only within the City of Perth road corridor)
Mid May 2023
Demolition and replacement kerbing works
Mid-May to Mid-June 2023
Path construction and service adjustments
Mid- June to Mid August 2023
* All dates are provisional pending permit approvals and suitable weather conditions.
Share July Construction Update on FacebookShare July Construction Update on TwitterShare July Construction Update on LinkedinEmail July Construction Update link
Shared Path construction between Poole Avenue and Mounts Bay Road has been completed and is open, along with the internal Western Path within Kings Park, refer to the updated Detour Map below.
Demolition works for the remaining section of the path have now been completed. Night works are due to commence from the 20 July 2023, please refer to details contained in the notification letter.
Share Shared path construction between Poole Avenue and Stirling Highway on FacebookShare Shared path construction between Poole Avenue and Stirling Highway on TwitterShare Shared path construction between Poole Avenue and Stirling Highway on LinkedinEmail Shared path construction between Poole Avenue and Stirling Highway link
The path between Poole Avenue and Stirling Highway is under construction with the first section of new concrete poured the week commencing the 29 May 23, see pictures below. The remaining path sections to the front of University Hall shall be poured Monday 12 June 23.
The driveway access into University Hall from Winthrop Avenue will be closed between the 19 -26 June 23 to allow for a raised crossing to be installed. Please follow the pedestrian and road detour signs around the work site.