Consultation has concluded
Following the replacement of the automatic retractable bollards within the Hay Street and Murray Street Malls in 2020, The City of Perth (City) has committed to upgrading the remaining adjacent static bollards.
The upgrade will also include the installation of new seating to the front of the Perth Underground, within the Mall. This new seating will form a certified barrier preventing unauthorised vehicular access entering the Mall.
The upgrade works are scheduled to run from August to November 2022 and will be staged to minimise disruption – please refer to the attached location maps. Construction for each stage is anticipated as follows:
STAGE
LOCATION
ANTICIPATED DATES *
TIMES
1
Hay St Mall exit Intersection of William St and Hay St
08/08/2022 to 09/09/2022
0530 to 1530
2
Hay St Mall entrance Intersection of Barrack St and Hay St
12/09/2022 to 27/09/2022
0530 to 1530
3
Murray St Mall exit Intersection of Barrack St and Murray St
30/09/2022 to 17/10/2022
0530 to 1530
4
Murray St Mall entrance Intersection of William St and Murray St
18/10/2022 to 09/11/2022
0530 to 1530
5
Target Lane
09/11/2022 to 21/11/2022
0530 to 1530
*Subject to activity permit approval and environmental conditions
ENQUIRIES
If you have any questions or enquiries regarding the Mall Safety Bollards Project, please contact the Customer Experience Team via email at info@cityofperth.wa.gov.au(External link) or call on 08 9461 3333.
Following the replacement of the automatic retractable bollards within the Hay Street and Murray Street Malls in 2020, The City of Perth (City) has committed to upgrading the remaining adjacent static bollards.
The upgrade will also include the installation of new seating to the front of the Perth Underground, within the Mall. This new seating will form a certified barrier preventing unauthorised vehicular access entering the Mall.
The upgrade works are scheduled to run from August to November 2022 and will be staged to minimise disruption – please refer to the attached location maps. Construction for each stage is anticipated as follows:
STAGE
LOCATION
ANTICIPATED DATES *
TIMES
1
Hay St Mall exit Intersection of William St and Hay St
08/08/2022 to 09/09/2022
0530 to 1530
2
Hay St Mall entrance Intersection of Barrack St and Hay St
12/09/2022 to 27/09/2022
0530 to 1530
3
Murray St Mall exit Intersection of Barrack St and Murray St
30/09/2022 to 17/10/2022
0530 to 1530
4
Murray St Mall entrance Intersection of William St and Murray St
18/10/2022 to 09/11/2022
0530 to 1530
5
Target Lane
09/11/2022 to 21/11/2022
0530 to 1530
*Subject to activity permit approval and environmental conditions
ENQUIRIES
If you have any questions or enquiries regarding the Mall Safety Bollards Project, please contact the Customer Experience Team via email at info@cityofperth.wa.gov.au(External link) or call on 08 9461 3333.