Mall Safety Bollards

Share Mall Safety Bollards on Facebook Share Mall Safety Bollards on Twitter Share Mall Safety Bollards on Linkedin Email Mall Safety Bollards link

Consultation has concluded

Following the replacement of the automatic retractable bollards within the Hay Street and Murray Street Malls in 2020, The City of Perth (City) has committed to upgrading the remaining adjacent static bollards.

The upgrade will also include the installation of new seating to the front of the Perth Underground, within the Mall. This new seating will form a certified barrier preventing unauthorised vehicular access entering the Mall.

The upgrade works are scheduled to run from August to November 2022 and will be staged to minimise disruption – please refer to the attached location maps. Construction for each stage is anticipated as follows:


STAGE

LOCATION

ANTICIPATED DATES *

TIMES

1

Hay St Mall exit
Intersection of William St and Hay St

08/08/2022 to 09/09/2022

0530 to 1530

2

Hay St Mall entrance
Intersection of Barrack St and Hay St

12/09/2022 to 27/09/2022

0530 to 1530

3

Murray St Mall exit
Intersection of Barrack St and Murray St

30/09/2022 to 17/10/2022

0530 to 1530

4

Murray St Mall entrance
Intersection of William St and Murray St

18/10/2022 to 09/11/2022

0530 to 1530

5

Target Lane

09/11/2022 to 21/11/2022

0530 to 1530

*Subject to activity permit approval and environmental conditions


ENQUIRIES

If you have any questions or enquiries regarding the Mall Safety Bollards Project, please contact the Customer Experience Team via email at info@cityofperth.wa.gov.au(External link) or call on 08 9461 3333.


Following the replacement of the automatic retractable bollards within the Hay Street and Murray Street Malls in 2020, The City of Perth (City) has committed to upgrading the remaining adjacent static bollards.

The upgrade will also include the installation of new seating to the front of the Perth Underground, within the Mall. This new seating will form a certified barrier preventing unauthorised vehicular access entering the Mall.

The upgrade works are scheduled to run from August to November 2022 and will be staged to minimise disruption – please refer to the attached location maps. Construction for each stage is anticipated as follows:


STAGE

LOCATION

ANTICIPATED DATES *

TIMES

1

Hay St Mall exit
Intersection of William St and Hay St

08/08/2022 to 09/09/2022

0530 to 1530

2

Hay St Mall entrance
Intersection of Barrack St and Hay St

12/09/2022 to 27/09/2022

0530 to 1530

3

Murray St Mall exit
Intersection of Barrack St and Murray St

30/09/2022 to 17/10/2022

0530 to 1530

4

Murray St Mall entrance
Intersection of William St and Murray St

18/10/2022 to 09/11/2022

0530 to 1530

5

Target Lane

09/11/2022 to 21/11/2022

0530 to 1530

*Subject to activity permit approval and environmental conditions


ENQUIRIES

If you have any questions or enquiries regarding the Mall Safety Bollards Project, please contact the Customer Experience Team via email at info@cityofperth.wa.gov.au(External link) or call on 08 9461 3333.