October 2018

Concept Design

19 November 2018

Stakeholder Comment Period Open

07 December 2018

Stakeholder Comment Period Closed

January → June 2019

Detailed Design and Approvals

Detailed design for the Mount Street and Spring Street cycle upgrades is now complete and the approvals process is underway.

The planned Milligan Street cycle upgrades have been placed on hold and will be subject to an internal review.
December 2019 → January 2020

Construction

Construction of Stage 1 is underway and is scheduled for completion in January 2020.

The planned Milligan Street cycle upgrades have been placed on hold and will be subject to an internal review.