Causeway Pedestrian and Cyclist Bridges

Share Causeway Pedestrian and Cyclist Bridges on Facebook Share Causeway Pedestrian and Cyclist Bridges on Twitter Share Causeway Pedestrian and Cyclist Bridges on Linkedin Email Causeway Pedestrian and Cyclist Bridges link

Victoria Park to Perth CBD

Two Pedestrian and Cyclist bridges will be built alongside the existing Causeway Bridge, providing a 6-metre-wide shared path connecting the Victoria Park foreshore to Heirisson Island and Perth CBD with Point Fraser. Construction and ground improvement began in early 2023, with major works set to commence in mid-2023. The works will be completed throughout construction to minimise impacts on the community, foreshore park users and river vessels.

The Causeway Pedestrian and Cyclist bridges are jointly funded by the City of Perth, Australian and Western Australian governments as part of the Perth City Deal projects.

The project scope does not include the Causeway Bridge. Therefore, the existing road and path will still remain in place for cyclists, pedestrians and vehicles.


LOCATION AND DESIGN

The general location and design resulted from consultation with key stakeholders such as local governments, Traditional Owners, specialist groups, cycling/ boating authorities and other government agencies. Additional considerations and requirements include path and river users, future local developments on either side of the bridges and maritime height allowances. The select bridge locations are approximately 90 metres downstream of the existing Causeway traffic bridge, carefully chosen to minimise potential impacts on flora and fauna and improve path user connections or amenities.

Both bridges will emulate an s-shaped curve representing the sinuous movement of the Wagyl (rainbow serpent) while supporting the increased clearance heights above the river, minimising the number of existing trees impacted by construction. In addition, the curved bridge design will slow cyclists when travelling downhill before approaching key intersection points.

The design reflects and embeds Whadjuk Noongar culture, recognising the significance of Aboriginal heritage at Heirisson Island and the Swan River. Integral to the design are references to prominent Whadjuk Noongar people. These references will include the following:

  • Yagan is a young warrior leader represented by a boomerang-inspired pier.
  • Balbuk fought to retain the Swan-Coastal Plain’s over-development and is represented by two digging stick-inspired piers.

ENVIRONMENTAL CONSIDERATIONS

The Swan River and Heirisson Island are significant to Traditional Custodians of the area and the wider Perth community. Whilst the bridges and connecting path alignment have been designed to minimise environmental impacts and the removal of trees, some vegetation clearing will be required on Heirisson Island and Point Fraser in early 2023.

We will use bridge construction techniques that minimise environmental impacts, including marine, bird and land animals. The kangaroos currently living on Heirisson Island will remain throughout the project duration. A Construction Environmental Management Plan (CEMP), which defines the minimum management requirements during construction, will be developed in consultation with key stakeholders once all environmental surveys are complete.


FURTHER INFORMATION

For more information regarding the project, please visit the Main Roads website to view the Causeway Pedestrian and Cyclist Bridges project page.

  • Review the documents under the 'Documents' tab.
  • Check out the FAQs on the right-hand side.
  • View the Main Roads website by clicking here.


ENQUIRIES

If you have any further questions or enquiries regarding the Causeway Pedestrian and Cyclist Bridges, please contact Main Roads via email at enquiries@mainroads.wa.gov.au or call on 138 138.

Victoria Park to Perth CBD

Two Pedestrian and Cyclist bridges will be built alongside the existing Causeway Bridge, providing a 6-metre-wide shared path connecting the Victoria Park foreshore to Heirisson Island and Perth CBD with Point Fraser. Construction and ground improvement began in early 2023, with major works set to commence in mid-2023. The works will be completed throughout construction to minimise impacts on the community, foreshore park users and river vessels.

The Causeway Pedestrian and Cyclist bridges are jointly funded by the City of Perth, Australian and Western Australian governments as part of the Perth City Deal projects.

The project scope does not include the Causeway Bridge. Therefore, the existing road and path will still remain in place for cyclists, pedestrians and vehicles.


LOCATION AND DESIGN

The general location and design resulted from consultation with key stakeholders such as local governments, Traditional Owners, specialist groups, cycling/ boating authorities and other government agencies. Additional considerations and requirements include path and river users, future local developments on either side of the bridges and maritime height allowances. The select bridge locations are approximately 90 metres downstream of the existing Causeway traffic bridge, carefully chosen to minimise potential impacts on flora and fauna and improve path user connections or amenities.

Both bridges will emulate an s-shaped curve representing the sinuous movement of the Wagyl (rainbow serpent) while supporting the increased clearance heights above the river, minimising the number of existing trees impacted by construction. In addition, the curved bridge design will slow cyclists when travelling downhill before approaching key intersection points.

The design reflects and embeds Whadjuk Noongar culture, recognising the significance of Aboriginal heritage at Heirisson Island and the Swan River. Integral to the design are references to prominent Whadjuk Noongar people. These references will include the following:

  • Yagan is a young warrior leader represented by a boomerang-inspired pier.
  • Balbuk fought to retain the Swan-Coastal Plain’s over-development and is represented by two digging stick-inspired piers.

ENVIRONMENTAL CONSIDERATIONS

The Swan River and Heirisson Island are significant to Traditional Custodians of the area and the wider Perth community. Whilst the bridges and connecting path alignment have been designed to minimise environmental impacts and the removal of trees, some vegetation clearing will be required on Heirisson Island and Point Fraser in early 2023.

We will use bridge construction techniques that minimise environmental impacts, including marine, bird and land animals. The kangaroos currently living on Heirisson Island will remain throughout the project duration. A Construction Environmental Management Plan (CEMP), which defines the minimum management requirements during construction, will be developed in consultation with key stakeholders once all environmental surveys are complete.


FURTHER INFORMATION

For more information regarding the project, please visit the Main Roads website to view the Causeway Pedestrian and Cyclist Bridges project page.

  • Review the documents under the 'Documents' tab.
  • Check out the FAQs on the right-hand side.
  • View the Main Roads website by clicking here.


ENQUIRIES

If you have any further questions or enquiries regarding the Causeway Pedestrian and Cyclist Bridges, please contact Main Roads via email at enquiries@mainroads.wa.gov.au or call on 138 138.

  • Next Steps to Bridge Completion - May to December 2024

    Share Next Steps to Bridge Completion - May to December 2024 on Facebook Share Next Steps to Bridge Completion - May to December 2024 on Twitter Share Next Steps to Bridge Completion - May to December 2024 on Linkedin Email Next Steps to Bridge Completion - May to December 2024 link
    supporting image

  • Path detour change at Point Fraser

    Share Path detour change at Point Fraser on Facebook Share Path detour change at Point Fraser on Twitter Share Path detour change at Point Fraser on Linkedin Email Path detour change at Point Fraser link
    supporting image

    As construction continues for the Causeway Pedestrian and Cyclist Bridges Project, a new path detour will occur at Point Fraser. A section of the shared path, adjacent to the river, will be closed until late 2024, to facilitate safe marine works including access into the river for construction.

    The existing path detour, implemented along the northern side of Riverside Drive in January 2024, will remain in place with temporary traffic management and controls. Path users will continue to be given priority to cross the closed section of Riverside Drive, which is currently open to construction traffic only.

    Path users accessing these areas are advised to take extra care and follow signage. We thank you for your patience and apologise in advance for any inconvenience.

    Figure 1 Path detours at Point Fraser – Effective mid-February 2024 until late 2024

  • Point Fraser Path Detour

    Share Point Fraser Path Detour on Facebook Share Point Fraser Path Detour on Twitter Share Point Fraser Path Detour on Linkedin Email Point Fraser Path Detour link
    supporting image

    In preparation for constructing the Causeway Pedestrian and Cyclist Bridges Project, works are being undertaken at Point Fraser to relocate a key water pipeline which is over 100 years old. Path detours will be in place during these works to safely direct path users around the work area.

    The shared path along Riverside Drive will be closed, with path users detoured around the work site via the temporary shared path and scaffold ramp along the foreshore. This detour will be in place from midday Tuesday 26th September 2023, for approximately three months.

    Please always proceed with caution and adhere to signage throughout the area. We thank you for your patience and apologise in advance for any inconvenience.

    Access to On the Point businesses, About Bike Hire, the CPP car park and the underpass to East Perth will be maintained.

    If you have any questions, please contact 138 138 or email enquiries@mainroads.wa.gov.au

    More information about this project is also available on the project webpage and you can also subscribe for updates: www.mainroads.wa.gov.au/causeway-path

  • Nightworks at Riverside Drive, Point Fraser

    Share Nightworks at Riverside Drive, Point Fraser on Facebook Share Nightworks at Riverside Drive, Point Fraser on Twitter Share Nightworks at Riverside Drive, Point Fraser on Linkedin Email Nightworks at Riverside Drive, Point Fraser link
    supporting image

    In preparation for constructing the Causeway Pedestrian and Cyclist Bridges Project, ongoing investigation works will be undertaken on Riverside Drive and Adelaide Terrace at Point Fraser, prior to relocating a key water pipeline.

    The works will be undertaken at night, requiring the closure of one westbound (citybound) lane on Riverside Drive and Adelaide Terrace just past the existing Causeway Traffic Bridge. Traffic will be detoured around the work site and traffic management will be put in place.

    Riverside Drive and Adelaide Terrace Roadworks

    • Monday 24 July 2023

    • Nightworks - 8:00pm - 5.00am

    • Westbound (citybound) lane closed

    • Riverside Drive exit ramp closed

    • Speed reduction to 40km/h near the works area

    • Eastbound lanes will not be impacted

    The reduction in speed and temporary lane closures are necessary to safely undertake the works. Road conditions may be unfamiliar so allow additional time to pass through this area.

    Please always proceed with caution and adhere to the speed limit and signage throughout the area. We thank you for your patience and apologise in advance for any disruption or inconvenience.

    If you have any questions, please contact 138 138 or email enquiries@mainroads.wa.gov.au

    More information about this project is also available on the project webpage and you can also subscribe for updates: www.mainroads.wa.gov.au/causeway-path


  • Causeway Pedestrian and Cyclist Bridges Project Path Detours at Point Fraser

    Share Causeway Pedestrian and Cyclist Bridges Project Path Detours at Point Fraser on Facebook Share Causeway Pedestrian and Cyclist Bridges Project Path Detours at Point Fraser on Twitter Share Causeway Pedestrian and Cyclist Bridges Project Path Detours at Point Fraser on Linkedin Email Causeway Pedestrian and Cyclist Bridges Project Path Detours at Point Fraser link
    supporting image

    In preparation for constructing the Causeway Pedestrian and Cyclist Bridges Project, works are being undertaken at Point Fraser to relocate a key water pipeline which is over 100 years old. These works commenced in May and are expected to be completed by October 2023.

    Path detours – Stage 1 and Stage 2

    Path detours will be in place during these works to safely direct path users around the work area. The detours will be established in stages over approximately six weeks in order to enable works at different locations. Please always proceed with caution and adhere to signage throughout the area. We thank you for your patience and apologise in advance for any inconvenience.

    Access to On the Point businesses, About Bike Hire, the CPP car park and the underpass to East Perth will be maintained.

    Stage 1: A portion of the shared path along Riverside Drive will be closed, with path users detoured around the work site and along the foreshore. This will allow for direct site access and site set up.

    Approximate duration: Two weeks, starting Thursday 13 July 2023.

    Figure 1 - Path Detour Stage 1 - Early July


    Stage 2: A portion of the shared path along the foreshore will be closed, and path users will be detoured around the work site and to the path along Riverside Drive. This will allow for water pipe works.

    Approximate duration: Two days in late July 2023.

    Figure 2 - Path Detour Stage 2 - Late July

    Further path detours will occur as the project progresses. More information will be provided in advance of these changes.

    Vegetation impacts

    A small amount of vegetation has been removed to enable access for machinery to conduct these works. As the project progresses, further removal of vegetation will be necessary to facilitate the construction of the bridge abutment on Point Fraser. Vegetation removed will be replaced or repurposed within the project site where possible. To find out more about how the Causeway Link Alliance is mitigating and managing environmental impacts, click here to view the Environment Fact Sheet.

    Further information

    If you have any questions, please contact 138 138 or email enquiries@mainroads.wa.gov.au

    More information about this project is also available on the project webpage and you can also subscribe for updates: www.mainroads.wa.gov.au/causeway-path

  • Causeway Pedestrian and Cyclist Bridges Project - Path Detour at McCallum Park

    Share Causeway Pedestrian and Cyclist Bridges Project - Path Detour at McCallum Park on Facebook Share Causeway Pedestrian and Cyclist Bridges Project - Path Detour at McCallum Park on Twitter Share Causeway Pedestrian and Cyclist Bridges Project - Path Detour at McCallum Park on Linkedin Email Causeway Pedestrian and Cyclist Bridges Project - Path Detour at McCallum Park link
    supporting image

    To construct the Causeway Pedestrian and Cyclist Bridges Project, a path detour will be implemented at McCallum Park, restricting access to the foreshore in front of the works site for pedestrians and cyclists.

    This will change how pedestrians and cyclists use the path network, with the detour now changing the network to one temporary shared path to safely direct path users around the work area. The detour will be in place from late June 2023 and will remain in place for the duration of the project, until the end of 2024.

    As pedestrians and cyclists will be using the same path, please always proceed with caution and adhere to signage throughout the area. We thank you for your patience and apologise in advance for any inconvenience.

Page published: 28 May 2024, 04:19 PM