Consultation has concluded
The City of Perth’s Minor Urban Interventions program seeks to enhance city spaces through small projects that support residents, local businesses and social interaction in the community. This year’s focus is re-imagining and revitalising underutilised streets to support street based activation.
After receiving numerous requests from members of the West Perth community for basketball facilities we have identified Thelma Street as an ideal location to trial a small court. This project will re-purpose a portion of un-used space at the western cul-de-sac while still maintaining full access to businesses along the street.
Construction is scheduled to commence mid March 2021. Please subscribe to receive progress updates, or continue to check back to this page.
The City of Perth’s Minor Urban Interventions program seeks to enhance city spaces through small projects that support residents, local businesses and social interaction in the community. This year’s focus is re-imagining and revitalising underutilised streets to support street based activation.
After receiving numerous requests from members of the West Perth community for basketball facilities we have identified Thelma Street as an ideal location to trial a small court. This project will re-purpose a portion of un-used space at the western cul-de-sac while still maintaining full access to businesses along the street.
Construction is scheduled to commence mid March 2021. Please subscribe to receive progress updates, or continue to check back to this page.
Share Construction Update on FacebookShare Construction Update on TwitterShare Construction Update on LinkedinEmail Construction Update link
The main construction has now been completed on the mini basketball court. Due to freight delays, the seating is estimated to be delivered and installed in approximately 3 weeks.
Signup Banner
to ask a question
Timeline
Design plans finalised February 2021
Thelma Street Basketball Court Trial - West Perth has finished this stage
Construction scheduled to commence mid-March 2021
Thelma Street Basketball Court Trial - West Perth has finished this stage
Estimated to take 2 weeks to complete.
Construction complete (estimated April 2021)
Thelma Street Basketball Court Trial - West Perth is currently at this stage
Construction of the basketball court has been completed, awaiting the delivery of the seating with the estimated installation date being early-to-mid April 2021