Road Renewals Program 2022-2023

Share Road Renewals Program 2022-2023 on Facebook Share Road Renewals Program 2022-2023 on Twitter Share Road Renewals Program 2022-2023 on Linkedin Email Road Renewals Program 2022-2023 link

Consultation has concluded

The City of Perth will shortly be undertaking essential road renewals and drainage upgrade works throughout the City and these works will run from August 2022 to June 2023 throughout various locations within City of Perth boundaries.


Location

Description of Works
Project Dates

Fitzgerald Street (from John to James Street East bound)

Road Resurfacing

Saturday, 15 October 2022

The Avenue (between 25 The Avenue and 9 The Avenue)

Road Resurfacing

Monday, 17 October 2022

Bellevue Terrace (from Cul-De-Sac to Cliff Street North)

Road Resurfacing

Tuesday 18 - Wednesday, 19 October 2022

Brook Street (Between Royal and Glyde Street)

Road Resurfacing

Saturday, 5 November 2022

Park Road Between Tareena Street to Spica Lane

Road Resurfacing

Saturday, 12 November 2022

Monash Avenue Between Kanimbla Road and Ferdinand Lane

Road Resurfacing

Saturday, 26 and Sunday, 27 November 2022

Ventnor Avenue Between Ord Street to Richardson Street

Road Resurfacing

Saturday, 3 December to Sunday, 4 December 2022

Moore Street (Hill St to Cul De Sac)

Road Resurfacing

Saturday, 18 March to Sunday, 19 March 2023

Royal Street Between Lord Street to Hill Street

Road Resurfacing

Saturday, 25 February to Sunday, 26 February 2023

Winthrop Avenue - Southbound (Between Stirling HWY to Poole Ave)

Road Resurfacing

Sunday, 19 March to Thursday, 23 March 2023

Riverside Drive - Westbound (Between Plain Street to Barrack Square)

Road Resurfacing

Monday, 13 February to Thursday, 30 March 2023

Colin Street (Between Richardson Street to Hay Street)

Road Resurfacing

Saturday, 1 April to Sunday, 2 April 2023

Mill Street (Mounts Bay Road to St Georges Terrace)

Road Resurfacing - Customer Notification Letter

Saturday, 13 May to Sunday, 14 May 2023

East Parade Roundabout (Intersection of East Parade, Brook Street and Plain Street)Road Resurfacing - Customer Notification Letter
Sunday, 14 May to Thursday, 18 May 2023
Wellington Street - Eastbound (Between Elder Street to Milligan Street) and Wellington Street and Milligan Street Intersection
Road Resurfacing - Customer Notification Letter
Tuesday, 23 May to Friday, 26 May 2023
Kings Park Rd - Thomas St to Fraser Ave (WBND)

Road Resurfacing - Customer Notification LetterSunday, 28 May to Friday, 2 June 2023
Loftus St - Mitchell Fwy off-ramp to Railway St (SBND)

Road Resurfacing - Customer Notification Letter
Sunday, 11 June to Saturday, 17 June 2023

William Street (Between Hay Street to Murray Street)

Road Resurfacing - Customer Notification Letter

Sunday, 18 June to Thursday, 22 June 2023

St Georges Terrace and William Street Intersection

Road Resurfacing - Customer Notification Letter

Sunday, 25 June to Tuesday, 27 June 2023


Please note the following dates and times are subject to weather permitting.

How will these works impact you?

  • During this period, approved traffic management will be in place.
  • Pedestrian and local resident access will be maintained, however, some delays should be expected.

NEED TO KNOW MORE?

The City appreciates your understanding during the period of these works. Should you have any concerns, please contact:

  • Direct enquiries to City of Perth: Abdulla Lugumaan, Project Manager, 9461 3165 (during normal business hours for projects 1,5,6)
  • Direct enquiries to City of Perth: Sharmistha Saha, Asset Planning Engineer, 9461 3753 (during normal business hours projects 7,8,9)
  • City Asphalt Contractor (Downer EDI): Mr. Iain Campbell (Manager) - 0427 493 920 and Mr. Richard Firth, Downer EDI Works (Site Supervisor) - 0418 669 695 or for general enquiries, Downer Group on 9365 9999
  • Contact City of Perth Customer Experience Team - 9461 3333 or via email info@cityofperth.wa.gov.au


The City of Perth will shortly be undertaking essential road renewals and drainage upgrade works throughout the City and these works will run from August 2022 to June 2023 throughout various locations within City of Perth boundaries.


Location

Description of Works
Project Dates

Fitzgerald Street (from John to James Street East bound)

Road Resurfacing

Saturday, 15 October 2022

The Avenue (between 25 The Avenue and 9 The Avenue)

Road Resurfacing

Monday, 17 October 2022

Bellevue Terrace (from Cul-De-Sac to Cliff Street North)

Road Resurfacing

Tuesday 18 - Wednesday, 19 October 2022

Brook Street (Between Royal and Glyde Street)

Road Resurfacing

Saturday, 5 November 2022

Park Road Between Tareena Street to Spica Lane

Road Resurfacing

Saturday, 12 November 2022

Monash Avenue Between Kanimbla Road and Ferdinand Lane

Road Resurfacing

Saturday, 26 and Sunday, 27 November 2022

Ventnor Avenue Between Ord Street to Richardson Street

Road Resurfacing

Saturday, 3 December to Sunday, 4 December 2022

Moore Street (Hill St to Cul De Sac)

Road Resurfacing

Saturday, 18 March to Sunday, 19 March 2023

Royal Street Between Lord Street to Hill Street

Road Resurfacing

Saturday, 25 February to Sunday, 26 February 2023

Winthrop Avenue - Southbound (Between Stirling HWY to Poole Ave)

Road Resurfacing

Sunday, 19 March to Thursday, 23 March 2023

Riverside Drive - Westbound (Between Plain Street to Barrack Square)

Road Resurfacing

Monday, 13 February to Thursday, 30 March 2023

Colin Street (Between Richardson Street to Hay Street)

Road Resurfacing

Saturday, 1 April to Sunday, 2 April 2023

Mill Street (Mounts Bay Road to St Georges Terrace)

Road Resurfacing - Customer Notification Letter

Saturday, 13 May to Sunday, 14 May 2023

East Parade Roundabout (Intersection of East Parade, Brook Street and Plain Street)Road Resurfacing - Customer Notification Letter
Sunday, 14 May to Thursday, 18 May 2023
Wellington Street - Eastbound (Between Elder Street to Milligan Street) and Wellington Street and Milligan Street Intersection
Road Resurfacing - Customer Notification Letter
Tuesday, 23 May to Friday, 26 May 2023
Kings Park Rd - Thomas St to Fraser Ave (WBND)

Road Resurfacing - Customer Notification LetterSunday, 28 May to Friday, 2 June 2023
Loftus St - Mitchell Fwy off-ramp to Railway St (SBND)

Road Resurfacing - Customer Notification Letter
Sunday, 11 June to Saturday, 17 June 2023

William Street (Between Hay Street to Murray Street)

Road Resurfacing - Customer Notification Letter

Sunday, 18 June to Thursday, 22 June 2023

St Georges Terrace and William Street Intersection

Road Resurfacing - Customer Notification Letter

Sunday, 25 June to Tuesday, 27 June 2023


Please note the following dates and times are subject to weather permitting.

How will these works impact you?

  • During this period, approved traffic management will be in place.
  • Pedestrian and local resident access will be maintained, however, some delays should be expected.

NEED TO KNOW MORE?

The City appreciates your understanding during the period of these works. Should you have any concerns, please contact:

  • Direct enquiries to City of Perth: Abdulla Lugumaan, Project Manager, 9461 3165 (during normal business hours for projects 1,5,6)
  • Direct enquiries to City of Perth: Sharmistha Saha, Asset Planning Engineer, 9461 3753 (during normal business hours projects 7,8,9)
  • City Asphalt Contractor (Downer EDI): Mr. Iain Campbell (Manager) - 0427 493 920 and Mr. Richard Firth, Downer EDI Works (Site Supervisor) - 0418 669 695 or for general enquiries, Downer Group on 9365 9999
  • Contact City of Perth Customer Experience Team - 9461 3333 or via email info@cityofperth.wa.gov.au